BOQ builder โ€” Section A + BJSGsample ยท 15

The stock hub builds Section A โ€” the system spec, pulling from aluminium master, finishes and freight โ€” and pushes it to the JEB entities. Each receiving entity then edits Section B locally (materials, glass, hardware, install labour) using its own margin codes. STC rating is captured at template level so the quotation can pull it.

Section A (stock hub): system spec including STC rating ยท pushed to JEB entities ยท cost-locked. Section B (per entity):local glass, fire-rated, powdercoat, hardware and installation ยท edited locally ยท uses that entity's own margin codes ยท multiple margin codes per BOQ are supported.
System
WS1
STC rating
35 dB
Frame profile
JEB 004M
Margin code (this BOQ)
M-PR-006 (32%)
Pushed to
JHK ยท JSG ยท JKL
Section A โ€” Supply only (from the list price engine)
PositionProduct codeDescriptionFrameTotal qtyUOMUnit rateTotal
TopJEB 004MSlimline 26x45mm glazing mainframe/doorframeGF 110pcโ†’ list priceโ€”
BottomJEB 004Slimline glazing frameGF 110pcโ†’ list priceโ€”
BottomJEB 005Slimline glazing beadGF 110pcโ†’ list priceโ€”
STAKE 3Aluminium corner stake (50pc/bag)0.4bagโ†’ list priceโ€”
innerWEDGE 3B or GPVC wedge #3 (100m/roll)0.35rollโ†’ list priceโ€”
T&BV774 Foam RubberSelf adhesive foam rubber 6x3.2mm1.65rollโ†’ list priceโ€”
TOTAL SUPPLY ONLYUSD โ€”
1.02)E โ€” EXCLUDES 12mm glass panel12sqm
Section B โ€” Local materials & installation (from local price maintenance)
DescriptionQtyUOMUnit rate (SGD)Total (SGD)Unit rate (client)Total (client)
Install single glass frame & glass12sqm34.50414.0034.50414.00
Install transom0LMโ†’ local rateโ€”โ†’ local rateโ€”
Install post0nos12.000.0012.000.00
Custom post0nosโ†’ local rateโ€”67.800.00
Local standard powdercoat (50-60um)0LMโ†’ local rateโ€”4.070.00
Glass cleaning for single glaze12sqm3.0036.003.0036.00
Total local costsโ€”450.00
GP on installation112.50
Quote price โ€” Labour, materials & installation562.50